188 Phoenix 9.76.0 Installation and Setup Manual 806410
8–Diagnostics
To test the operator console:
1. From the Main screen, select Setups > Diagnostics > Operator Interface.
2. To test the USB port, touch it on the picture on the Operator Interface screen then follow the instructions on the
screen.
3. To test the lights for Station 1 or 2, touch the corresponding light on the picture on the Operator Interface screen
then follow the instructions on the screen.
4. You can also operate any component on the front panel of the CNC and watch the corresponding component on the
screen. Verify that the operation of the component on the screen matches what you do on the panel
If the test for a single component fails, replace that component. If multiple components fail, contact your OEM or system
integrator to replace the ribbon cable to the front panel board, the front panel board, or both.